TNPSC Group 1 · 2015 Preliminary Examination
194. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same work in 2 days, then what is the time taken by 15 men and 20 boys to complete the same type of work?
Answer:
A.
4 days